JR
Prezados
Had Aris 7.2 integrated with Solution Manager.
We performed the upgrade Aris 7.2 to 9.6 and we need to reconnect the Solution Manager.
What procedures do we need to make not lose the references of the processes already mapped?
att,
Hi Romero,
These are the rough steps:
- Register a SAP Server in the administration \ SAP section
- Register the SAP project
- Configure the SAP project in the same way as you synchronized in ARIS 7.2 (method configuration etc)
- activate the Project (Change status to active)
Regards,
Ronald