MS
Hi,
I would like to assign a throughput time to a human task in APG.
In general that is very easy by using a constant and connect it in the data flow.
But as far as i know this does not take actual working days into account. So if I say I would like to have the task done in one day and the task is created on Friday late afternoon the due date would be Saturday late afternoon. I would like it to have it due on Monday (considering it the next working day) afternoon.
Is there any way to put something like a schedule behind those assignments that takes weekends and holidays into account?
Regards,
Mathias