I am trying to synchronize a project from SAP Solution Manager to ARIS and am getting a strange error (see below). The problem is something with the filter because it works with no problems when I use the Entire Method filter.
Can someone please point me in the right direction to fix the filter?
Thanks,
Ken
=====
SAP transport request: SOLK900604
==================================================================
Creating: Start model 'JCS_SAND - JCS Project Prototyping and Sanbox SolMan Project'
Synchronizing: Start model 'JCS_SAND - JCS Project Prototyping and Sanbox SolMan Project'
Loading: Scenario 'ADMIN - Project Plan'
Loading: Scenario 'OTC - Sales Order Management (MTO)'
Loading: Scenario 'OTC - Master Data Management'
Loading: Scenario 'OTC - Returns Management'
Loading: Scenario 'PTP - Master Data Management'
Loading: Scenario 'PTP - Direct and Indirect Procurement'
Loading: Scenario 'STP - Inventory Management'
Loading: Scenario 'RTR - Master Data Management'
Loading: Scenario 'RTR - Financial Accounting'
Loading: Scenario 'RTR - Managerial Accounting'
Loading: Scenario 'STP - Master Data Management'
Loading: Scenario 'STP - Manufacture Execution'
Loading: Scenario 'BPP (Work Instructions)'
Loading: Scenario 'TECH - OTC'
Loading: Scenario 'TECH - PTP'
Loading: Scenario 'TECH - RTR'
Loading: Scenario 'TECH - STP'
Synchronizing: System landscape
Unable to determine the logical components. Please check whether the assignment relationships between the project element and this model are maintained consistently.
End time: Fri Feb 26 00:21:25 CET 2010
Duration: 0 day(s), 0 hour(s), 0 minute(s), 3 second(s).
Hi Ken,
If the problem still not solved, could you check if your filter allows the required assignments from application system type object?
when transferring system landscape, it requires assignment of of application system type diagram enabled from application system type object.
I hope this is helpful,
BR,
Shayam